Change Task Type for Multiple Tasks
- Task Type can be changed for multiple tasks at the same time.
- Select multiple tasks in the Task Grid, then right-click More > Set Task Type, then choose the type of task to change them to (Work, Monitor, Meeting, Summary, Milestone, Major Milestone). Click here to learn how to select multiple tasks.
/Whats%20New/Feb%202025/Feb%201%2c%202025%20-%20Set%20task%20type%20for%20multiple%20tasks%20-%2001.png?width=670&height=390&name=Feb%201%2c%202025%20-%20Set%20task%20type%20for%20multiple%20tasks%20-%2001.png)
- The default values for Duration, Work Per Day, and Total Work are also updated when changing from one Task Type to another.
- The following table shows the default values for each Task Type, where the asterisk (*) is a function of the resource's availability (hours/day), shown here as 5 hours/day.
Task Type Duration (days) Work Per Day* (hours/day) Total Work* (hours)
Work 1 5 5 Monitor 1 0 0 Meeting 1 1 1 Summary 5, if 'Auto' is not selected
N/A N/A Milestone N/A N/A N/A Major Milestone N/A N/A N/A - Watch this video [1:11 min] for a demonstration.
- Need a hand? Contact a Customer Success Engineer today!