Instant Replay
Instant Replay
- You can animate baseline studies using Instant Replay! Instant Replay gives you the ability to see how the project plan has been changing over time (like a video).
- Specify the Start From option for the baseline...
- Specific Date / Time
- Start of Task Execution
- Number of Past Weeks (rolling start date based on the number of weeks selected)
- Number of Past Days (rolling start date based on the number of days selected)
- Select a Replay Increment to determine how often to pull baseline information. The shorter the increment, the greater the resolution, and the longer it takes to run the replay.
- No (Not an Instant Replay)
- Daily (pull baseline data daily from the start date to today)
- Weekly (pull baseline data weekly from the start date to today)
- Bi-Weekly (pull baseline data bi-weekly from the start date to today)
- Monthly (pull baseline data monthly from the start date to today)
- Shazam! Check out this video for a quick demo!
- Specify the Start From option for the baseline...