Copy/Paste Tasks as Predecessors/Successors

  1. Tasks can be copied then pasted as predecessors/successors in another task.

  2. Select one or more tasks you want as predecessors or successors in another task (target task), then right-click and select More > Copy Tasks.

  3. Open Task Properties of the target task, then click the Links page.

  4. Select paste in the list of predecessors and/or successors.

  5. Voila, the tasks are now predecessors/successors to the target task! Note: Links are not copied/pasted for Shared Subtasks, Parent Summaries, existing Links, or tasks in other projects.